- March 29th, 2015, 8:05 pm
#74807
For two straight hours this afternoon/evening, the Fury crew dispatched 40 trains one hour, then 41 the next. Their goal is 48, but Mike said B&M told them the ride can handle 50-55 per hour.
At one point they were getting so fast, a loaded train (Train 2) would roll out of the station and would stop and wait to be advanced to the lift hill. The previous train (Train 1) would have to hit the 91 degree turn around before the second train would move to the left hill. While the second train was waiting to be advanced to the lift hill, the third train would already be loading in the station. (Hope that makes sense.)
At one point they were getting so fast, a loaded train (Train 2) would roll out of the station and would stop and wait to be advanced to the lift hill. The previous train (Train 1) would have to hit the 91 degree turn around before the second train would move to the left hill. While the second train was waiting to be advanced to the lift hill, the third train would already be loading in the station. (Hope that makes sense.)